Title: Amd 1 to Agmt PR00007042 with Stantec for final design, engineering, professional services and construction administration for reconstruction of CSAH 32 (Penn Ave) in Richfield (CP 2120700), ext period to 12/31/31, and incr NTE by $4,500,000 for a new total NTE of $6,300,000 (TAA-Complete Streets)
Attachments: 1. Map of Penn Ave Reconstruction CP 2120700
Related files: 25-0097
Item Description:
title
Amd 1 to Agmt PR00007042 with Stantec for final design, engineering, professional services and construction administration for reconstruction of CSAH 32 (Penn Ave) in Richfield (CP 2120700), ext period to 12/31/31, and incr NTE by $4,500,000 for a new total NTE of $6,300,000 (TAA-Complete Streets)
end

Resolution:
body
BE IT RESOLVED, that the County Administrator be authorized to execute Amendment 1 to PR00007042 with Stantec Consulting Services, Inc. to provide final design, engineering, professional services, and construction administration for the reconstruction of County State Aid Highway (CSAH) 32 (Penn Avenue) from 75th Street to Trunk Highway (TH) 62 (the Crosstown) in the city of Richfield, county project (CP) 2120700, extending the period to December 31, 2031 and increasing the contract by $4,500,000 for a revised not to exceed (NTE) total amount of $6,300,000; that upon review and approval by the County Attorney’s Office, the Chair of the Board be authorized to sign the amendment on behalf of the county; and that the Controller be authorized to disburse the funds as directed.
end

Background:
The county, in partnership with the City of Richfield, is leading a project to reconstruct Penn Avenue. This corridor is identified on the county’s Toward Zero Deaths Action Plan High Injury Network. The project will modernize the roadway with a Complete and Green Streets design, including:

New pavement, curb and gutter
Accessibility, safety, and multi-modal improvements
Intersection improvements
Stormwater and public utility upgrades

In March 2025, the county entered into Agreement PR00007042 with Stantec Consulting Services, Inc. for preliminary design, engineering and professional services at a county cost of $1,800,000 (Resolution 25-0097).

The county will continue to engage with the community to develop a design that meets the project goals and community needs.

Current Request: This request seeks authorization to execute...