File #: 25-0055    Version: 1
Type: Immediate Approvals Status: Agenda Ready
File created: 1/13/2025 In control: Board of Hennepin County Commissioners
On agenda: 1/28/2025 Final action:
Title: Award Contract FC00000165 to Sheehy Construction Company for the ACF Men's Generator 2 project, $1,379,300
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Item Description:
title
Award Contract FC00000165 to Sheehy Construction Company for the ACF Men's Generator 2 project, $1,379,300
end

Resolution:
body
BE IT RESOLVED, that the award of Contract FC00000165 to Sheehy Construction Company for the ACF Men's Generator 2 project (Sub Project 1010687, Capital Project 0031730), in the amount of $1,379,300 be approved; that the Chair of the Board be authorized to sign the contract on behalf of the county after the performance and payment bonds have been properly executed; and that the Controller be authorized to disburse funds as directed.
end

Background:
This request is for a new 1,000-kilowatt generator at the men's ACF facility. This new generator will work in conjunction with the existing generator to provide full redundancy during utility power outages. The new generator will have a separate diesel belly tank and will be tied into the building's bulk underground diesel tank supply for extended utility outages. New electrical switch/parallel gear will be provided to operate both generators in a load sharing or full redundant configuration. Civil work is included to add louvers for venting of engine and fuel tank exhaust through the roof of the building.

The addition of a new generator will provide for better confidence to weather unexpected utility outages. It also provides redundancy during generator maintenance periods. This addition to the facility's electrical service will enhance the life safety systems and institution security.

Through a best value procurement process, a Request for Proposals was released on October 8, 2024. Four (4) proposals were received. Based on the results of interviews, cost, and written submittals, Sheehy Construction Company, received the highest score, and is recommended for this project.

Current Request:
This request seeks approval of Contract FC00000165 to Sheehy Construction Company for the ACF Men's Generator 2 project (Sub Project 1010687, Capital Project 0031730), in...