Skip to main content

File #: 25-0275    Version: 1
Type: Resolution Status: Approved
File created: 6/27/2025 In control: Board of Hennepin County Commissioners
On agenda: 7/8/2025 Final action: 7/29/2025
Title: Execute Contract No. CM00001439 with Millerbernd Manufacturing Co. to purchase traffic signal poles for maintenance replacements, est county cost $2,000,000 (Fund 10)
Attachments: 1. RESOLUTION
Item Description:
title
Execute Contract No. CM00001439 with Millerbernd Manufacturing Co. to purchase traffic signal poles for maintenance replacements, est county cost $2,000,000 (Fund 10)
end

Resolution:
body
BE IT RESOLVED, that the County Administrator be authorized to execute Contract No. CM00001439 with Millerbernd Manufacturing Company to purchase mast arm signal poles with anchor bolts for maintenance replacements during the period August 1, 2025 through December 31, 2027 at an estimated cost of $2,000,000; that following review and approval by the County Attorney's office, the Chair of the Board be authorized to sign the contract on behalf of the county; and that the Controller be authorized to disburse funds as directed.
end

Background:
The county needs a means to purchase traffic signal poles to replace existing poles as maintenance needs dictate. Currently, Public Works has minimal stock of mast arm signal poles. Staff engaged Millerbernd Manufacturing Company, who is the sole source signal steel supplier in Minnesota, to purchase these materials.

Staff is seeking the county board's authorization to enter into a contract with Millerbernd Manufacturing Company to procure traffic signal poles for maintenance replacements, because the total purchase price exceeds the annual allowable limits of $250,000 for a sole source supplier.

Funding for the purchase of signal equipment is available in Public Works Fund 10.

Current Request: This request seeks authorization to execute Contract No. CM00001439 with Millerbernd Manufacturing Company to purchase signal equipment during the period August 1, 2025 through December 31, 2027, at an estimated cost of $2,000,000.

Impact/Outcomes: These installations will support the county's Mobility 2040 goals, climate action, and disparity reduction efforts by improving accessibility, mobility, and safety for multimodal transportation.

recommendation
Recommendation from County Administrator: Recommend Approv...

Click here for full text