Title: Award a set-aside Contract FC00000149 to Moltron Builders, Inc. for the 625 New All Gender Restrooms project, NTE $1,148,005
Attachments: 1. RESOLUTION
Item Description:
title
Award a set-aside Contract FC00000149 to Moltron Builders, Inc. for the 625 New All Gender Restrooms project, NTE $1,148,005
end

Resolution:
body
BE IT RESOLVED, that pursuant to set-aside authority authorized under Minn. Stat. ? 471.345, Contract FC0000149 to Moltron Builders, Inc. for the 625 New All Gender Restrooms project (Sub-Project 1010354, Capital Project 1007468), in the amount of $1,148,005 be approved; that the Chair of the Board be authorized to sign the contract on behalf of the county after the performance and payment bonds have been properly executed; and that the Controller be authorized to disburse funds as directed.
end

Background:
Built in 1981, the 625 Building is a 539,000 gross square foot, 17 story office building which was acquired by the county in 2018.

This project will make several improvements to the 625 Building including:
* adding all gender restrooms and all gender locker room facilities to the first floor of the building - while the upper floors of the building have all gender restrooms, there are no public-facing all gender restrooms adjacent to the auditorium. Adding two all gender restrooms will satisfy the code required fixture count and will align with the county's gender affirming policy as described in Resolution No. 22-0216.
* adding all gender locker rooms adjacent to the existing gendered locker room facilities. All locker rooms will include toilets, changing areas, and showers. Bike lockers are available in the Fifth Avenue ramp.
* improvements to the adjacent existing exercise facility. These improvements will include new HVAC and ceilings with LED lighting to meet building standards. Some equipment left by the previous tenant will be reused.
* new code-required railing in the public atrium is also included in this project.

Through a best value procurement process, a Request for Proposals was released on April 23, 2024. Two (2) proposal were received. Moltron Builders, Inc. receive...

Click here for full text