Title: Neg work authorization under Principal Agmt PR00002760 with Short Elliot Hendrickson, Inc. for final design engineering and professional services for the reconstruction of Cedar Avenue (CSAH 152) in Minneapolis; amend budget (CP 2220200); cost: NTE $900,000 ($300,000 state aid, $300,000 property tax, $300,000 recv)
Attachments: 1. Map of CP 2220200 on CSAH 152 in Minneapolis, 2. RESOLUTION
Item Description:
title
Neg work authorization under Principal Agmt PR00002760 with Short Elliot Hendrickson, Inc. for final design engineering and professional services for the reconstruction of Cedar Avenue (CSAH 152) in Minneapolis; amend budget (CP 2220200); cost: NTE $900,000 ($300,000 state aid, $300,000 property tax, $300,000 recv)
end

Resolution:
body
BE IT RESOLVED, that the County Administrator be authorized to negotiate a work authorization under Principal Agreement PR00002760 with Short Elliot Hendrickson, Inc. (SEH) for final design engineering and professional services for the reconstruction of County State Aid Highway (CSAH) 152 (Cedar Avenue) between CSAH 3 (Lake Street) and 24th Street in the city of Minneapolis, county project (CP) 2220200, at a cost not to exceed $900,000; that following review and approval by the County Attorney's office, the Chair of the Board be authorized to sign the work authorization on behalf of the county; and that the Controller be authorized to disburse funds as directed; and

BE IT FURTHER RESOLVED, that $300,000 in property tax be transferred from CP 2201200: Project Delivery TSCA to CP 2220200: CSAH 152 - Reconstruct Cedar Ave fr Lake St to 24th St; that the revenue from Minneapolis be increased by $300,000 (from $120,000 to $420,000); that the total revenues for CP 2220200 be increased by $600,000 (from $1,130,000 to $1,730,000) as part of the 2024 Capital Budget; and that the Controller be authorized to transfer, accept and disburse funds as directed.
end

Background:
The county, in partnership with the city, is leading roadway reconstruction on Cedar Avenue between Lake and 24th streets. In 2023, through a competitive selection process, the county contracted with SEH for preliminary project design at a cost not to exceed $800,000 under Principal Agreement PR00002760 (Resolution 23-0213).

Substantial public engagement has been occurring for the project, including signage, surveys, online mapping, commun...