File #: 24-0283    Version: 1
Type: Resolution Status: Approved
File created: 6/24/2024 In control: Board of Hennepin County Commissioners
On agenda: 6/25/2024 Final action: 7/23/2024
Title: Authorization to acquire properties for the Hennepin Healthcare replacement parking ramp (CP 1010908)
Attachments: 1. RESOLUTION
Item Description:
title
Authorization to acquire properties for the Hennepin Healthcare replacement parking ramp (CP 1010908)
end

Resolution:
body
BE IT RESOLVED, that the Hennepin Healthcare replacement parking ramp is necessary for the future deployment of healthcare services and that the project is for a public purpose and for public use; and

BE IT FURTHER RESOLVED, that the use of the "quick take" procedures of Chapter 117 of Minnesota Statutes is necessary and expedient; and

BE IT FURTHER RESOLVED, that the County Administrator be authorized to acquire fee title and/or easements by purchase or condemnation, and to negotiate agreements for real estate and consulting services necessary for the acquisition of property for the Hennepin Healthcare replacement parking ramp; that upon review and approval by the County Attorney's Office, the Chair be authorized to execute agreements, easements, and deeds on behalf of the county; and that the County Administrator be authorized to execute all other documents necessary to complete the acquisitions on behalf of the county; and that the Controller be authorized to disburse funds as directed; and

BE IT FURTHER RESOLVED, that capital project (CP 1010908) HHS Parking Replacement project be identified in the 2024 Capital Budget with an appropriation of $70,000,000; with the acquisition of land funded by transfers from the General Fund and the balance of initial project costs funded by the transfer of the remaining general obligation bonding budget authority from the Purple Parking Expansion (CP 1008705) project to the new (CP 1010908) HHS Parking Replacement project; and

BE IT FURTHER RESOLVED, that the administrator is directed to estimate additional project costs for consideration as part of the 2025 Capital Budget and 2025-2029 Capital Improvement Program process.
end

Background:
History:
The Hennepin Healthcare replacement parking ramp (the "Project") is necessary to replace parking capacity that will be l...

Click here for full text