Title: Amend the 2025 Capital Budget to increase Library Replacement (CP 1004468); transfer $2,000,000 in existing budget authority from six identified capital projects
Attachments: 1. Westonka Budget Forms, 2. Westonka Library Replacement Budget Transfer Summary, 3. RESOLUTION 25-0256 Edited
Item Description:
title
Amend the 2025 Capital Budget to increase Library Replacement (CP 1004468); transfer $2,000,000 in existing budget authority from six identified capital projects
end

Resolution:
body
BE IT RESOLVED, that the Capital Budget for the Westonka Library Replacement project (CP 1004468) be increased from $17,500,000 to $19,500,000, with the $2 million increase funded with a transfer of existing capital budget authority from six identified capital projects to cover construction costs; and the Controller be authorized to transfer and disburse funds as directed...end

Background:
History:
The current Westonka Library, located at 2079 Commerce Boulevard in Mound, MN, is an 8,600 gross square foot, one-story building, situated on a 1.68-acre site with surface parking for 48 vehicles. Board Resolution 23-0409 approved the schematic design for a new 12,000 gross square foot, single-story, building with 29 parking stalls, EV-ready infrastructure to serve two stalls, and landscaping and site improvements. The new net-zero building will align with the county's climate action plan through its use of renewable geothermal and solar energy.

In Fall 2024, a best-value request for proposals was issued, garnering six proposals on December 4, 2024. Of the six proposals received, the lowest was 25.5 percent over the professional cost estimate of $11,420,000 and the second to highest proposal was just under 70 percent over the cost estimate. The solicitation was cancelled, and the architect was directed to value engineer the project to lower the cost. At the county's direction, the architect also retained a second professional cost estimator for the value-engineered designed. The construction estimate for the value-engineered design was $13,000,000.

The value-engineered design retained the project's previously approved net-zero energy features, gross square footage, programmatic features and overall aesthetics. Savings were accomplished through re...