Item Description:
title
Neg Agmt PW 02-09-26 with Crystal for cost participation and maintenance for CSAH 102 (Douglas Drive) in Crystal, CP 2211300, (est recv $290,000)
end
Resolution:
body
BE IT RESOLVED, that the County Administrator be authorized to negotiate Agreement PW 02-09-26 with the City of Crystal for cost participation and maintenance responsibilities for the design, right-of-way acquisition, and construction of multimodal safety improvements on CSAH 102 (Douglas Drive) between 32nd Avenue and Fairview Avenue, County Project (CP) 2211300, at an estimated receivable amount of $290,000; that upon review and approval by the County Attorney’s Office, the Chair of the Board be authorized to sign the agreement on behalf of the county; and that the Controller be authorized to accept funds as directed.
end
Background:
Hennepin County, in collaboration with the City of Crystal, is leading a project to improve multimodal safety along CSAH 102 (Douglas Drive), CP 2211300. The CSAH 9 (42nd Avenue) intersection, included with the project, is identified on the county’s Toward Zero Deaths Action Plan - Highway Injury Network. The project, planned for construction in 2027, will include the following:
• Improved pedestrian crossings
• Traffic calming
• Signal replacement and upgrades
Current Request: This request seeks authorization to negotiate Agreement PW 02-09-26 with the City of Crystal for cost participation and maintenance responsibilities related to multimodal safety improvements on Douglas Drive between 32nd Avenue and Fairview Avenue, at an estimated county receivable of $290,000.
Impacts/Outcomes: This project supports the county’s Toward Zero Deaths Action Plan, American with Disabilities Act (ADA) Transition Plan, Climate Action Plan, and disparity elimination efforts by improving accessibility, mobility, and safety for all people using the corridor.
recommendation
Recommendation from County Administrator: Recommend Approval