File #: 23-HCRRA-0018    Version: 1
Type: RRA New Business Status: Approved
File created: 6/8/2023 In control: Hennepin County Regional Railroad Authority
On agenda: 6/27/2023 Final action: 6/27/2023
Title: Neg Amd 10 to Agmt PR00000689 with Met Council and Hennepin County for HC Southwest Light Rail Transit ("METRO Green Line Extension") Project (CP 1005876), extend end date to 01/31/2024 with no incr to the NTE
Attachments: 1. 19-HCRRA-0037_Resolution.pdf, 2. 19-HCRRA-0038_Resolution.pdf, 3. 20-HCRRA-0012_Resolution.pdf, 4. 20-HCRRA-0031_Resolution.pdf, 5. 20-HCRRA-0039_Resolution.pdf, 6. 20-HCRRA-0052_Resolution.pdf, 7. 21-HCRRA-0039_Resolution.pdf, 8. 22-HCRRA-0019_Resolution.pdf, 9. 22-HCRRA-0045_Resolution.pdf, 10. RESOLUTION
Related files: 24-HCRRA-0003
Item Description:
title
Neg Amd 10 to Agmt PR00000689 with Met Council and Hennepin County for HC Southwest Light Rail Transit ("METRO Green Line Extension") Project (CP 1005876), extend end date to 01/31/2024 with no incr to the NTE
end

Resolution:
body
BE IT RESOLVED, that the County Administrator be authorized to negotiate Amendment 10 to Agreement PR00000689, Capital Grant Agreement for the Southwest Corridor Light Rail Transit (METRO Green Line Extension) Project with the Metropolitan Council and Hennepin County, extending the grant activity period from June 30, 2023, to January 31, 2024, and making certain clarifying changes, with no increase to the maximum grant amount of $978,080,704; that following review and approval by the County Attorney's Office, the Chair of the Board be authorized to sign the amendment on behalf of the County; and that the Controller be authorized to disburse funds as directed; and

BE IT FURTHER RESOLVED, that the Board approvals herein do not waive any obligations of the Metropolitan Council under any relevant agreement.
end

Background:
On May 31, 2018, the Hennepin County Regional Railroad Authority ("HCRRA") adopted Resolution 18-HCRRA-0027, committing up to $199,548,000 of HCRRA funding to the Southwest Corridor Light Rail Transit (METRO Green Line Extension) Project (CP 1000899) ("Project"). On November 15, 2018, HCRRA adopted Resolution 18-HCRRA-0056, which among other actions, authorized negotiation of a new grant agreement with the Metropolitan Council ("Council") and Hennepin County, Agreement PR00000689 (the "Agreement"), to replace prior funding agreements and be the sole funding source for all Project activities through the end of August 2019.

The Agreement was then negotiated and executed, with a not to exceed amount of $434,901,943 in total funds from Hennepin County (up to $347,921,554) and HCRRA (up to $86,980,389). The funded activities included civil construction work authorized by the Federal Trans...

Click here for full text