File #: 25-0023    Version: 1
Type: Resolution Status: Referred
File created: 12/31/2024 In control: Public Works Committee
On agenda: 1/7/2025 Final action:
Title: Neg Agmt PW 02-40-25 with MnDOT, city of Plymouth and Three Rivers Park District for improvements on CSAH 73, total county cost $1,060,000 ($1,000,000 Transportation Advancement Account - Active Transportation, $60,000 County Bonds)
Attachments: 1. Map of CP 285070 on CSAH 73
Item Description:
title
Neg Agmt PW 02-40-25 with MnDOT, city of Plymouth and Three Rivers Park District for improvements on CSAH 73, total county cost $1,060,000 ($1,000,000 Transportation Advancement Account - Active Transportation, $60,000 County Bonds)
end

Resolution:
body
BE IT RESOLVED, that the County Administrator be authorized to negotiate Agreement PW 02-40-25 (State Contract No. 1058416) with the Minnesota Department of Transportation (MnDOT), city of Plymouth and Three Rivers Park District for cost participation and maintenance responsibilities relating to multimodal and safety improvements, county project (CP) 2850700 and fiber optic conduit system improvements, (CP) 1006393 along County State Aid Highway (CSAH) 73 between Sunset Trail/Zachary Lane and South Shore Drive/10th Avenue in the city of Plymouth at a county cost not to exceed $1,000,000, (CP) 2850700 and estimated at $60,000, (CP) 1006393, that upon review and approval by the County Attorney's Office, the Chair of the Board be authorized to sign the agreement on behalf of the county; and that the Controller be authorized to disburse funds as directed.
end

Background:
The city of Plymouth, in coordination with the county, MnDOT and Three Rivers Park District, is leading a reconstruction project on CSAH 73 generally between Sunset Trail/Zachary Lane and South Shore Drive/10th Avenue. The project, which is anticipated to begin construction in 2025, includes the following multi-modal and safety improvements with new county-owned fiber optic systems.

* Realignment of CSAH 73
* Accessibility and signal upgrades
* Roundabout
* New regional trail
* Storm water/drainage improvements

The agreement identifies the city to lead the design and deliver the project. After completion, the ownership of the current alignment of CSAH 73 from Sunset Trail to TH 55 will be transferred to the city of Plymouth. Additional ownership and maintenance responsibilities will be assigned consistent with...

Click here for full text