Title: Amd 2 to Agmt PR00004057 with Bolton and Menk, Inc for final design engineering and construction support for CSAH 5 (Franklin Avenue) reconstruction, CP 2172600, (incr NTE $3,460,000 State Aid Regular and ext period to 06/01/28)
Attachments: 1. Map CP 2172600 in Minneapolis (1)
Related files: 24-0193
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Item Description:
title
Amd 2 to Agmt PR00004057 with Bolton and Menk, Inc for final design engineering and construction support for CSAH 5 (Franklin Avenue) reconstruction, CP 2172600, (incr NTE $3,460,000 State Aid Regular and ext period to 06/01/28)
end

Resolution:
body
BE IT RESOLVED, that the County Administrator be authorized to execute Amendment 2 to Agreement PR00004057 with Bolton and Menk, Inc. to provide final design engineering and construction support for County State Aid Highway (CSAH) 5 (Franklin Avenue) from CSAH 22 (Lyndale Avenue) to Chicago Avenue in Minneapolis, County Project (CP) 2172600, increasing the contract amount by $260,000 for a not to exceed total of $3,460,000 and extending the end date to June 1, 2028; that upon review and approval by the County Attorney's Office, the Chair of the Board be authorized to sign the amendment on behalf of the county; and that the Controller be authorized to disburse funds as directed
end

Background:
Hennepin County, in partnership with the City of Minneapolis, is leading the reconstruction of Franklin Avenue between Lyndale and Chicago avenues, CP 2172600. The project will modernize the roadway with a complete and green streets design, including:

* New pavement, sidewalk, curb and gutter
* Stormwater and drainage improvements
* Accessibility, multimodal and safety improvements
* Street lighting and replacement of city utilities

Bolton and Menk, Inc. is under contract with the county to provide design, engineering and professional services for the reconstruction of CSAH 5 (Franklin Avenue), CP 2172600 (Resolutions 22-0088, and 24-0193). Additional final design engineering and construction support is needed to complete the project.

Current Request: This request seeks authorization to execute Amendment 2 to Agreement PR00004057 with Bolton and Menk, Inc. for final design engineering and construction support, increasing the contract amount to $3,460,000 and extending the period to June 1, 2...