File #: 25-0100    Version: 1
Type: Resolution Status: Approved
File created: 3/5/2025 In control: Board of Hennepin County Commissioners
On agenda: Final action: 3/25/2025
Title: Neg Agmt PW 09-06-25 with Mound for pedestrian improvements along CSAH 15; transfer funds from CP 2183300 to CP 2201100 & incr capital budget for CP 2201100 (county cost: $500,000 county bonds, $220,000 state aid)
Attachments: 1. Map: CP 2201113 in Mound, 2. RESOLUTION
Item Description:
title
Neg Agmt PW 09-06-25 with Mound for pedestrian improvements along CSAH 15; transfer funds from CP 2183300 to CP 2201100 & incr capital budget for CP 2201100 (county cost: $500,000 county bonds, $220,000 state aid)
end

Resolution:
body
BE IT RESOLVED, that the County Administrator be authorized to negotiate Agreement PW 09-06-25 with the City of Mound for pedestrian improvements and cost participation and maintenance responsibilities for County State Aid Highway (CSAH) 15 (Shoreline Drive) between Fairview Lane and the Seton Channel Bridge, county project (CP) 2201100, at an estimated cost of $720,000; that following review and approval by the County Attorney's Office, the Chair of the Board be authorized to sign the agreement on behalf of the county; and that the Controller be authorized to disburse funds as directed; and

BE IT FURTHER RESOLVED, that the revenues for CP 2201100 - Cost Participation and Partnerships 2024-2028 be increased by $220,000 in State Aid Regular transferred from CP 2183300 - Safety and Asset Management 2019-2023; that the overall project budget for CP 2201100 be increased by $220,000 (from $20,775,000 to $20,995,000) as part of the 2025 Capital Budget; and the Controller be authorized to transfer and disburse funds as directed.
end

Background:
The city, in collaboration with the county, is leading a sidewalk improvement project along Shoreline Drive (CSAH 15) from Fairview Lane to the Seton Channel Bridge. The agreement identifies the city as the lead agency for construction and assigns maintenance responsibilities after the project is constructed later this year.

Funding for these improvements along Shoreline Drive is available through the county's Cost Participation and Partnerships program (CP 2201100), with expenses tracked in its subproject CP 2201113, based on the following:

* County financing 100% of the pedestrian ramp costs, which was requested to be included in the city's sidewalk project due t...