Title: Neg Agmt PW 57-73-25 with Wright County for cost participation and maintenance of County Line Road SE (CR 139) in Independence and Delano (Project 4613900), (est Hennepin County cost: $350,000, 2027 Transp Ops Operating Budget)
Attachments: 1. Map of Project 4613900 in Independence and Delano, 2. RESOLUTION

Item Description:

title

Neg Agmt PW 57-73-25 with Wright County for cost participation and maintenance of County Line Road SE (CR 139) in Independence and Delano (Project 4613900), (est Hennepin County cost: $350,000, 2027 Transp Ops Operating Budget)

end

 

Resolution:

body

BE IT RESOLVED, that the Hennepin County Administrator be authorized to negotiate Agreement PW 57-73-25 with Wright County for cost participation and maintenance responsibilities related to the mill and overlay of County Line Road SE (also known as County Road 139), between Trunk Highway 12 and County State Aid Highway 50 (also known as Rebecca Park Road), in the cities of Independence and Delano (Project 4613900), at an estimated Hennepin County cost of $350,000; and

BE IT FURTHER RESOLVED, that following review and approval by the Hennepin County Attorney’s Office, the Chair of the Hennepin County Board of Commissioners be authorized to sign the agreement on behalf of Hennepin County; and that the Controller be authorized to disburse funds as directed.

end

 

Background:

Hennepin County and Wright County share ownership of County Line Road SE (County Road 139). The last surface treatment was completed in 2009, and the pavement surface is currently rated as “fair.” Wright County has proposed to lead a project to mill and overlay the roadway between Trunk Highway 12 and Rebecca Park Road (CSAH 50), located in the cities of Independence and Delano. 

Funding for this project is planned in the 2027 Transportation Operations Operating Budget under pavement preservation and maintenance.

Current Request: Authorize the County Administrator to negotiate Agreement PW 57-73-25 with Wright County for cost participation and maintenance responsibilities, related to the mill and overlay of County Road 139, between Trunk Highway 12 and Rebecca Park Road, in the cities of Independence and Delano (Project 4613900), at an estimated Hennepin County cost of $350,000. 

Impact/Outcomes: This action supports Hennepin County’s Toward Zero Deaths Action Plan, American with Disabilities Act (ADA) Transition Plan, Mobility 2040 Plan, Climate Action Plan, and disparity elimination efforts by improving safety and mobility for all people who use the road.

 

recommendation

Recommendation from County Administrator: Recommend Approval