Title: Amd 1 to Agmt PR00005002 with Kimley-Horn and Associates, Inc. for preliminary design engineering, professional services for Lyndale Avenue (CSAH 22) reconstruction in Minneapolis (CP 2052300), incr NTE county cost by $425,000; (county cost: NTE $1,672,000 state aid, $418,000 Minneapolis)
Attachments: 1. Map of CP 2052300 on CSAH 22, 2. RESOLUTION
Related files:

Item Description:

title

Amd 1 to Agmt PR00005002 with Kimley-Horn and Associates, Inc. for preliminary design engineering, professional services for Lyndale Avenue (CSAH 22) reconstruction in Minneapolis (CP 2052300), incr NTE county cost by $425,000; (county cost: NTE $1,672,000 state aid, $418,000 Minneapolis)

end

 

Resolution:

body

BE IT RESOLVED, that the county administrator be authorized to execute Amendment 1 to Agreement PR00005002 with Kimley-Horn and Associates, Inc. to provide preliminary design engineering and professional services for the reconstruction of County State Aid Highway (CSAH) 22 (Lyndale Avenue) from 31st Street to CSAH 5 (Franklin Avenue) in Minneapolis, county project (CP) 2052300, increasing the contract amount by $425,000 to a new not to exceed total of $2,090,000, with no change to the contract period; that upon review and approval by the County Attorney’s office, the Chair of the Board be authorized to sign Amendment 1 on behalf of the county; and that the Controller be authorized to disburse funds as directed.

end

 

Background:

This segment of Lyndale Avenue has reached the end of its service life and needs to be reconstructed. The county, in partnership with the City of Minneapolis, is leading the reconstruction project, CP 2052300. The proposed improvements include:

 

                     New pavement, drainage, curb and gutter, 

                     Accessibility, safety and traffic signal upgrades, and

                     Complete and green streets elements.

 

As the project develops, the team will continue its community engagement to develop a preferred design that meets the project goals and serves the needs of the community. 

In 2023 the county entered into Agreement PR00005002 with Kimley-Horn and Associates, Inc. for preliminary design engineering and professional services for this project at a county cost not to exceed $1,665,000 (Resolution 23-0074). Kimley-Horn was selected for this project through the county’s enterprise contracting process, and it is committed to meeting the small and minority business goal of 15% set for the project, in addition to utilizing 20% of the contract for small and emerging business enterprises.

Additional services are needed to complete the preliminary design and engagement. Project funding is available in the project budget, CP 2052300, with expenses tracked in its associated subprojects CP 2052302 and CP 2052303. Kimley-Horn will continue to provide preliminary design engineering and professional services, including project management, engagement, traffic and alternatives analysis, layout for approval and environmental documentation. A future amendment to the agreement with Kimley-Horn is expected for final design, bidding and construction support.

Current Request:

This request seeks authorization to execute Amendment 1 to Agreement PR00005002 with Kimley-Horn and Associates, Inc. for preliminary design engineering and professional services for Lyndale Avenue reconstruction, CP 2052300, increasing the contract amount to a new not exceed total of $2,090,000.  

Impacts/Outcomes:

This action supports the county’s Mobility 2040, climate action and disparity reduction efforts by improving accessibility, mobility and safety along this corridor.

 