File #: 25-0079    Version: 1
Type: Resolution Status: Approved
File created: 2/3/2025 In control: Board of Hennepin County Commissioners
On agenda: 2/11/2025 Final action: 2/11/2025
Title: Design, Construction and Budget approvals for the HHS Parking Ramp Replacement Project (CP 1010908), Contract PR00007092 with Snow Kreilich Architects for architectural and engineering services, Contract FC00000166 with Kraus-Anderson Construction for preconstruction and construction services, project budget of $120,000,000
Attachments: 1. RESOLUTION

Item Description:

title

Design, Construction and Budget approvals for the HHS Parking Ramp Replacement Project (CP 1010908), Contract PR00007092 with Snow Kreilich Architects for architectural and engineering services, Contract FC00000166 with Kraus-Anderson Construction for preconstruction and construction services, project budget of $120,000,000

end

 

Resolution:

body

BE IT RESOLVED, that the following actions be approved for the HHS Parking Ramp Replacement project (CP 1010908);

- Authorization to proceed with project design development and construction documents;

- Authorization to proceed with execution of Guaranteed Maximum Price amendments, including for early bid packages which do not exceed the approved project budget of $120,000,000;

- Authorization to use contracted service vendors and commodity contracts as necessary for portions of the work, furnishings and equipment; and

BE IT FURTHER RESOLVED, that Contract PR00007092 with Snow Kreilich Architects for architectural and engineering services for all design phases through construction administration phase of the HHS Parking Ramp Replacement  Project (CP 1010908); for the period of March 17, 2025 through June 30, 2028, in an amount of $5,484,340.00 be approved; that the Chair of the Board be authorized to sign the contract on behalf of the county; and that the Controller be authorized to disburse funds as directed; and

BE IT FURTHER RESOLVED, that Contract No. FC000000166 with Kraus-Anderson Construction for an amount not to exceed $171,611.00 for preconstruction services; for the period of March 17, 2025 through November 30, 2025;  that the Chair of the Board be authorized to sign the contract on behalf of the county; and that the Controller be authorized to disburse funds as directed; and

BE IT FURTHER RESOLVED, that the County Administrator be authorized to award Guaranteed Maximum Price amendments to Kraus-Anderson Construction if the amendments are within the approved project budget; that the Chair of the Board be authorized to sign the Guaranteed Maximum Price amendments on behalf of the county after the performance and payment bonds have been properly executed; and that the Controller be authorized to disburse funds as directed; and

BE IT FURTHER RESOLVED, that the County Administrator be authorized to negotiate agreements for special inspections and testing and supplemental professional service agreements necessary to complete the project; that the Chair be authorized to execute agreements on behalf of the county; and that the Controller be authorized to disburse funds as directed.

end

 

Background:

History:
The Hennepin Healthcare replacement parking ramp (the ‘Project”) is necessary to replace parking capacity that will be lost when the parking ramps located on the Parkside block are taken down for future construction of a new hospital tower on that site.  The Project is located one block south of the planned new hospital tower, on Centennial Place between 9th Street and 10th Street South in Minneapolis.

This Project will provide parking for approximately 1,000 vehicles, a liner space along Chicago Ave, and a security office and a skyway connection to the existing HCMC campus.  Climate action initiatives include a photovoltaic array, stormwater retention, electric vehicle charging stations, secure bicycle parking and sustainable landscaping.  The Project will meet the Buildings, Benchmarks & Beyond (B3) Guidelines.

Numerous reviews and approvals by the city of Minneapolis will be necessary for the Project to proceed.  The Project is scheduled to be before the city of Minneapolis Planning Commission on March 10th, City Council Business, Housing & Zoning Committee on April 8th and City Council on April 17th. 

The design team, led by Snow Kreilich Architects, was chosen through a competitive process by a committee of representatives from Hennepin County and Hennepin Healthcare in December 2024.  The construction manager at risk, Kraus-Anderson Construction, was selected through a competitive process by a committee of representatives from both Hennepin County and Hennepin Healthcare earlier this year.  Pre-construction fees are fixed at $171,611 while the guaranteed maximum price (GMP) is to be developed towards the end of the design.  

Current Request:
This request is to authorize the county to award related contracts to design and construct a replacement parking ramp for Hennepin Healthcare provided the contracts do not exceed the approved project budget.

Impact/Outcomes:
Approval of this request will allow for the design and construction of the Hennepin Healthcare parking ramp, which in turn will allow for the demolition of the structures on the Parkside block and construction of a new hospital tower.

 

recommendation

Recommendation from County Administrator: Recommend Approval