File #: 23-0186    Version: 1
Type: Resolution Status: Approved
File created: 4/28/2023 In control: Board of Hennepin County Commissioners
On agenda: 5/2/2023 Final action: 5/16/2023
Title: Neg agmt PW 31-67-23 with the Metropolitan Council for multimodal improvements on CSAHs 36 and 37 (CP 2167301); (est recv $1,395,361)
Attachments: 1. BAR MAP-CSAH_36_37_CP_2167301_Multimodal_Improvements_Met_Council.pdf

Item Description:

title

Neg agmt PW 31-67-23 with the Metropolitan Council for multimodal improvements on CSAHs 36 and 37 (CP 2167301); (est recv $1,395,361)

end

 

Resolution:

body

BE IT RESOLVED, that the County Administrator be authorized to negotiate Agreement PW 31-67-23 with the Metropolitan Council (Met Council) for cost participation and maintenance of six Metro Transit E Line Arterial Bus Rapid Transit (ABRT) platforms to be constructed as part of the County State Aid Highways (CSAHs) 36 (University Avenue) and 37 (Fourth Street) multimodal improvement project in the city of Minneapolis, county project (CP) 2167301, at an estimated receivable of $1,395,361 ($1,283,732 capital, $111,629 operating); that upon review and approval by the County Attorney’s Office, the Chair of the Board be authorized to sign the agreement on behalf of the county; and 

BE IT FURTHER RESOLVED, that the revenues for CP 2167301 be adjusted to add $1,283,732 in cost participation from the Met Council; that the project budget for CP 2167301 be increased by the same amount from $19,180,000 to $20,463,732 in the 2023 Capital Budget; and that the Controller be authorized to accept and disburse funds as directed.

end

 

Background:

History: The county, in collaboration with the City of Minneapolis, Minnesota Department of Transportation (MnDOT), Met Council, and University of Minnesota, is leading a multimodal improvement project along University Avenue and Fourth Street from Interstate (I)-35W to Oak Street. This project will complement the Metro Transit E Line ABRT project planned along these corridors. 

In 2022, the board authorized negotiation and execution of various agreements relating to the project (Resolution 22-0199). After the passage of the resolution, the project scope expanded to include the construction of the six ABRT platforms along the project corridors as requested by the Met Council. By combining Met Council’s requested work into the county project, disruption to the community can be minimized.

Proposed Agreement PW 31-67-23 with Met Council stipulates that the county is the lead agency in project design, construction, and administration. Met Council will pay the county $1,395,361 for ABRT platforms to be constructed along the project corridor. Staff recommends that the revenues for CP 2167301 be adjusted to add $1,283,732 in cost participation from the Met Council, increasing the total project budget by the same amount from $19,180,000 to $20,463,732 in the 2023 Capital Budget. 

The project team collected feedback from the community through a virtual open house in spring 2020 and in-person open houses in the summer and fall of 2021. The county will continue its community engagement to share project status and updates. Construction is scheduled for spring 2024 with substantial completion in fall of 2025.  

Current Request: This request seeks authorization to negotiate and execute PW 31-67-23 with the Met Council for cost participation and maintenance of six E Line ABRT platforms to be constructed as part of CP 2167301, at an estimated receivable of $1,395,361.  

Impacts/Outcomes: This action supports the county’s Mobility 2040 goals, climate action and disparity reduction efforts by improving accessibility, mobility, and safety for multimodal transportation. The improvements will also provide connections to the future E Line ABRT. 

 

Budget table: CP 2167301 CSAH 36 & 37- Enhance bicycle facility fr I-35W to Oak St SE

Revenues:

Budget to Date

Current   Request

Future CIP   Requests

Total Project

Property Tax

100,000

 

 

100,000

Bonds-GO Roads

3,200,000

 

 

3,200,000

Federal - Other - Roads

5,500,000

 

 

5,500,000

Mn/DOT State Aid - Regular

6,450,000

 

 

6,450,000

Minneapolis

3,930,000

 

 

3,930,000

Metropolitan Council

 

1,283,732

 

1,283,732

Total

$19,180,000

$1,283,732

 

 20,463,732

Expenditures

 

 

Construction

13,300,000

1,116,289

 

14,416,289

Consulting

3,360,000

 

 

3,360,000

Contingency

2,520,000

167,446

 

2,687,446

Total

$19,180,000

$1,283,732

 

$20,463,732

 

 

recommendation

Recommendation from County Administrator: Recommend Approval