File #: 24-HCRRA-0015    Version: 1
Type: RRA New Business Status: Approved
File created: 7/18/2024 In control: Hennepin County Regional Railroad Authority
On agenda: 7/23/2024 Final action: 7/23/2024
Title: Neg Agmt PR00006308 with the City of Mpls relating to the replacement of 18th Avenue and Grand Avenue bridges (CP 1010999 and CP 1011000); NTE $4,262,414
Attachments: 1. Map of 18th and Grand Ave bridges in Minneapolis (CPs 1010999 & 1011000), 2. RESOLUTION

Item Description:

title

Neg Agmt PR00006308 with the City of Mpls relating to the replacement of 18th Avenue and Grand Avenue bridges (CP 1010999 and CP 1011000); NTE $4,262,414

end

 

Resolution:

body

BE IT RESOLVED, that the Executive Director be authorized to negotiate Agreement PR00006308 with the City of Minneapolis for cost participation in the replacement of the 18th Avenue (county project (CP) 1010999) and Grand Avenue (CP 1011000) bridges over the Midtown Corridor at a not to exceed (NTE) amount of $4,262,414; that following review and approval by the County Attorney’s Office, the Executive Director and Chair be authorized to sign the agreement on behalf of the authority; and that the Controller be authorized to disburse funds as directed; and

BE IT FURTHER RESOLVED,
that the Executive Director be authorized to execute the necessary temporary and permanent easements with the City of Minneapolis to allow for construction, operation, and maintenance of these bridges.

end

 

Background:

The Hennepin County Regional Railroad Authority (HCRRA) owns 20 original bridges that span the Midtown Corridor in south Minneapolis. These bridges, carrying city streets, are between 109 and 112 years old. The City of Minneapolis and HCRRA have partnered in previous projects to replace some bridges along the corridor. Last year, four bridges were replaced (Resolution 23-HCRRA-0007). The Agreement identifies the city to lead the design and deliver the project. After completion, the city will own, operate, and maintain the new bridges.

The Federal Government will provide approximately $12.3 million in federal funding for construction of the two bridges. The City of Minneapolis and HCRRA will share the non-federal/non-state expenses as detailed in the Agreement. The current cost estimate for the two bridges is $23.95 million ($12.30 million-federal; $7.39 million-city, and $4.26 million-HCRRA).

Project construction is anticipated to begin in 2026.

 

Current Request: This request is for authorization to:

                     Negotiate and execute Agreement PR00006308 with Minneapolis to replace 18th Avenue (CP 1010999) and Grand Avenue (CP 1011000) bridges at an NTE amount of $4,262,414; and

                     Enter into the necessary temporary and permanent easements to construct, own, operate, and maintain these bridges.

 

Impact/Outcomes: This action supports the county’s disparity reduction goals by maintaining critical transportation connections for all modes in Minneapolis.

 

recommendation

Recommendation from County Administrator: Choose an item.