File #:
|
24-0020R1
Version:
1
|
|
|
Type:
|
Resolution
|
Status:
|
Approved
|
On agenda:
|
|
Final action:
|
1/23/2024
|
Title:
|
Amd 2 to work authorization under Agmt PR00002153 and new Agmt PR00005723 with Bolton & Menk, Inc. relating to multimodal improvements along CSAHs 23, 52 and 952; amend budget for CP2182100; transfer funds (CP 2201200 to CP 2182100); county cost NTE: $4,000,000 State Aid, $1,497,000 Wheelage Tax est receivable $2,264,381
|
Item Description:
title
Amd 2 to work authorization under Agmt PR00002153 and new Agmt PR00005723 with Bolton & Menk, Inc. relating to multimodal improvements along CSAHs 23, 52 and 952; amend budget for CP2182100; transfer funds (CP 2201200 to CP 2182100); county cost NTE: $4,000,000 State Aid, $1,497,000 Wheelage Tax est receivable $2,264,381
end
Resolution:
body
BE IT RESOLVED, that the County Administrator be authorized to execute Amendment 2 to a work authorization under Agreement PR00002153 with Bolton & Menk, Inc. to provide final design engineering services for multimodal improvements along County State Aid Highway (CSAH) 52 (Hennepin Avenue) and CSAH 952 (First Avenue) between CSAH 23 (Main Street) and Eighth Street, and final design engineering services for a multi-use trail along Main Street between Hennepin Avenue and First Avenue in Minneapolis, CP 2182100, increasing the work authorization amount by $200,000 to a new not to exceed total of $1,650,000; that following review and approval by the County Attorney’s office, the Chair of the Board be authorized to sign the amendment on behalf of the county; and that the Controller be authorized to disburse funds as directed; and
BE IT FURTHER RESOLVED, that the County Administrator be authorized to execute Agreement PR00005723 with Bolton & Menk, Inc. to provide construction contract administration, inspection and surveying services relating to the multimodal improvements along Hennepin and First avenues from Main Street to Eighth Street, and along Main Street between Hennepin and First avenues, CP 2182100, in an amount not to exceed $1,497,000; that following review and approval by the County Attorney’s office, the Chair of the Board be authorized to sign the agreement on behalf of the county; and that the Controller be authorized to disburse funds as directed; and
BE IT FURTHER RESOLVED, that $1,497,000 in wheelage tax be transferred from CP 2201200 (Project Delivery 2024-2028) to CP 2182100 (CSAH 52 - Hennepin 1st Multimodal E Line fr Main St to 8th St); that the revenues for CP 2182100 be adjusted to add $4,000,000 in State Aid Regular, increasing the total from $5,590,000 to $9,590,000; $252,973 (fund source - State - Other - Roads) be added to CP 2182100, increasing the total from $1,438,435 to $1,691,408; that $1,711,408 in additional cost participation from the City of Minneapolis and $300,000 in additional cost participation from Minneapolis Park and Recreation Board (MPRB) be added to CP 218200, increasing the total from $4,311,838 to $6,023,246 for Minneapolis and $666,902 to $966,902 for MPRB; that the project budget for CP2182100 be increased by $7,761,381 from $20,490,240 to $28,251,621 as part of the 2024 Capital Budget; and that the Controller be authorized to transfer, accept and disburse funds as directed.
end
Background:
Hennepin County; in collaboration with the City of Minneapolis, Minneapolis Park and Recreation Board, Metropolitan Council, and Minnesota Department of Transportation; is leading a multimodal improvement project along Hennepin and First avenues from Main Street to Eighth Street and along Main Street between Hennepin and First avenues, which is scheduled for construction in 2024.
The county contracted with Bolton & Menk, Inc. through Agreement PR00002153 for design and engineering services at county cost not to exceed $1.1 million (Resolution 21-0424) and then amended the work authorization to increase the contract to $1.45 million for additional engineering services (Resolution 23-0142). Amendment 2 will allow for completion of the final design services, increasing the contract to $1.65 million. In addition, Bolton & Menk was selected from four firms that submitted proposals for construction administration, inspection, and surveying services. The firm is committed to meet the small and minority business project goal of 13%.
CP 2182100 went out to bid in fall 2023, and the ensuing bid opening on December 19, 2023 revealed higher construction costs than originally estimated. The increased costs result in additional budget authority needed to advance the project on schedule. Staff seek board authorization to increase the total budget for CP 2182100 to enable the county to deliver the project.
Current Request: This request seeks authorization to execute the following:
• Amendment 2 to the work authorization under Agreement PR00002153 with Bolton & Menk, Inc. for final design engineering services, increasing the work authorization amount by $200,000 to a new not to exceed amount of $1,650,000.
• Agreement PR00005723 with Bolton & Menk, Inc. for construction contract administration, inspection and surveying services for CP 2182100 at county not to exceed $1,497,000.
Additionally, this request seeks authorization to transfer $1,497,000 in wheelage tax from CP 2201200 to CP 2182100 and adjust the budget for CP 2182100 to add $4,000,000 in State Aid Regular, $252,973 (fund source State - Other - Roads), $1,711,408 in additional cost participation from the City of Minneapolis and $300,000 in additional cost participation from MPRB, increasing the total budget by $7,761,381 (from $20,490,240 to $28,251,621) as part of the 2024 Capital Budget.
Impacts/Outcomes: This project aligns with Hennepin County’s Mobility 2040 goals, climate action and disparity reduction efforts by improving accessibility, mobility and safety for multimodal transportation. The improvements will also provide connections to future E Line Arterial Bus Rapid Transit Stations.
Budget table 1: CP 2182100 CSAH 52 Hennepin/1st Multimodal E Line fr Main St to 8th St
REVENUE |
Budget to Date |
Current Request |
Future CIP Requests |
Total |
Wheelage Tax |
|
1,497,000 |
|
1,497,000 |
Federal - Other - Roads |
5,500,000 |
|
|
5,500,000 |
Mn/DOT State Aid - Regular |
5,590,000 |
4,000,000 |
|
9,590,000 |
State - Other - Roads |
1,438,435 |
252,973 |
|
1,691,408 |
Minneapolis |
4,311,838 |
1,711,408 |
|
6,023,246 |
Metropolitan Council |
1,033,065 |
|
|
1,033,065 |
Mpls Park & Rec Board |
666,902 |
300,000 |
|
966,902 |
Transfer - Metro Tax - Complete St |
1,950,000 |
|
|
1,950,000 |
|
|
|
|
|
Total |
$20,490,240 |
$7,761,381 |
|
$28,251,621 |
|
EXPENSE |
Budget to Date |
Current Request |
Future CIP Requests |
Total |
Right of Way |
1,700,000 |
|
|
1,700,000 |
Construction |
15,072,801 |
4,407,757 |
|
19,480,558 |
Consulting |
2,138,000 |
1,840,065 |
|
3,978,065 |
Contingency |
1,579,439 |
1,513,559 |
|
3,092,998 |
Total |
$20,490,240 |
$7,761,381 |
|
$28,251,621 |
Budget table 2: CP2201200 Project Delivery 2024-2028
REVENUE |
Budget to Date |
Current Request |
Future CIP Requests |
Total |
Wheelage Tax |
2,000,000 |
(1,497,000) |
8,000,000 |
8,503,000 |
Property Tax |
350,000 |
|
1,400,000 |
1,750,000 |
Mn/DOT State Aid - Regular |
500,000 |
|
2,000,000 |
2,500,000 |
|
|
|
|
|
Total |
$2,850,000 |
($1,497,000) |
$11,400,000 |
$12,753,000 |
|
EXPENSE |
Budget to Date |
Current Request |
Future CIP Requests |
Total |
Right of Way |
100,000 |
|
400,000 |
500,000 |
Consulting |
2,750,000 |
(1,497,000) |
11,000,000 |
2,253,000 |
Total |
$2,850,000 |
($1,497,000) |
$11,400,000 |
$12,753,000 |
recommendation
Recommendation from County Administrator: Recommend Approval
|