Neg Amd 1 to PW 05-44-25 with Three Rivers Park District for CSAH 66 multimodal safety improvements, CP 2211000, incr county NTE to $1,048,000 ($30,000 Property Tax, $880,000 Transportation Advancement Account - Active Transportation, and $138,000 Transportation Operations)
end
Resolution:
body
BE IT RESOLVED, that the County Administrator be authorized to negotiate Amendment 1 to Agreement PW 05-44-25 with Three Rivers Park District for cost participation related to the Three Rivers Park District Bassett Creek Regional Trail project; County Project 2211000 and subproject 2211005; increasing the county’s cost by $138,000 for a new amount not to exceed $1,048,000 to be financed with $30,000 in Property Tax, $880,000 in Transportation Advancement Account - Active Transportation and $138,000 from Transportation Operations; that upon review and approval by the County Attorney’s Office, the Chair of the Board be authorized to sign the amendment on behalf of the county; and that the Controller be authorized to disburse and accept the funds as directed.
end
Background:
The Bassett Creek Regional Trail will provide a connection between French Regional Park in Plymouth and Theodore Wirth Regional Park in Golden Valley. Three Rivers Park District, in coordination with the City of Golden Valley and the county, is leading a project to construct a multi-use trail to make this connection along CSAH 66 (Golden Valley Road) between CSAH 102 (Douglas Drive) and Theodore Wirth Parkway. The project team has been engaging with the community to share the design and gather feedback prior to constructing the improvements later this year.
The county previously entered into Agreement PW 05-44-25 with Three Rivers Park District for the project (Resolution 25-0102). The proposed amendment will increase the county’s not to exceed amount by $138,000 for pavement preservation work along Golden Valley Road. Funding for these improvements is available in County Project 2211000 - CSAH 66 Trail and Multimodal Safety Improvements, with expenses tracked in Subproject 2211005 - Basset Creek Regional Trail Mill and Overlay.
Current Request:
This request seeks authorization to negotiate Amendment 1 to PW 05-44-25 with Three Rivers Park District for the Bassett Creek Regional Trail Project (County Project 2211000 and Subproject 2211005) increasing the county’s cost by $138,000 for a new amount not to exceed $1,048,000.
Impacts/Outcomes:
These improvements will support the county’s Mobility 2040 goals, climate action and disparity reduction efforts by improving accessibility and enhancing safety for people walking, biking, and rolling.